Steam leak in Thermal Power Plant, collector tap, Pressure 170 bars, Temperature 220º

Intervention in the next 24 hours, sealing by placing a cashier, avoiding the consequent stoppage of production.

Steam leak in Thermal Power Plant, union nut. Pressure 40 bars, Temperature 160º

Intervention in the next 24 hours, placement of the cashier and subsequent sealing, achieving the best result to maintain production, avoiding an unscheduled plant shutdown.

Vapor leak in chemical plant through pore in pipe. Pressure 70 bars, Temperature 200ºC

5

Successful intervention, containment by placement of the cashier and subsequent sealing.

Steam leak in chemical plant, flange. Pressure 57 bars, Temperature 300ºC

6
7

Containment by clamp placement and subsequent sealing, achieving an excellent result until the scheduled shutdown of the plant.

Fuel oil leak in chemical plant by flange before tank without the possibility of isolation. Pressure 5 bars, Ambient temperature

comp1

Intervention carried out successfully, containment by clamping and subsequent sealing, avoiding the emptying and pouring of thousands of liters of fuel oil from a huge capacity tank.

Steam leak in company. Trash in valve. Pressure 12 bars, Temperature 220ºC

Intervention through valve encapsulation and subsequent sealing to avoid a production stop

Steam leak in a pulp and paper company, with encapsulation procedure. Pressure 15 bars, Temperature 240ºC